Completed Project · Hamilton
310 Limeridge Road West
A roughly 33,800-square-foot plaza roof replacement that expanded to address parapet and water-management concerns.
Discuss a Similar Property
Project Facts
Roof Replacement With Related Drainage and Parapet Work
This Hamilton plaza project covered approximately 33,800 square feet. The scope included removal of an existing two-ply modified roof system and installation of a Soprema two-ply system.
During the project, water-management and parapet-wall issues were identified. New parapet walls were installed, deteriorated existing parapet material was removed, and several drains and drain sumps were added.
Documented scope
- Removal of existing two-ply modified roofing
- Installation of a Soprema two-ply roofing system
- Removal of deteriorated parapet material
- Installation of new parapet walls
- Addition of drains and drain sumps

Roof Replacement Planning
Start With the Roof, Drainage and Building Conditions
A site review can help define whether the scope should include related water-management, parapet or transition work.